    fmsadmin RUN schedule should not complete before the end of the scheduled script

    Vincent_L

      Summary

      fmsadmin RUN schedule should not complete before the end of the scheduled script

      Product

      FileMaker Server

      Version

      11v2

      Operating system version

      Mac OS X 10.6.4

      Description of the issue

      If you run the command line

      fmsadmin RUN schedule [SCHEDULE_NUMBER]

      it will launch the schedule but won't wait the end of the schedule to give back the hand to the command line. That makes impossible to script things that needs the schedule taks to be complete

      Steps to reproduce the problem

      run fmsadmin RUN schedule [SCHEDULE_NUMBER] and it will give back the hand to the cli instantly

      Expected result

      the comand line should be busy till the scheduled task is not completed

      Actual result

      command line is resumes instantly

      Exact text of any error message(s) that appear

      Schedule 'Today' will run now.

      Workaround

      None